Technical and Executive Deputy of Qom Urban Train Organization says fifty percent of Qom Metro radio equipment entered the workshop.
Elaborating on the progress of the installation of radio equipment in the first phase of line one, Dariush Zareh said half of the equipment is supplied and being installed and the rest will enter the workshop soon.
Zareh said the equipment required for the Qom metro radio network includes wireless devices, repeaters, leaky cables and batteries.
He went on to say that radio equipment is installed in the metro to establish communication between personnel, the station manager, the command center and the guides, emphasizing the important role it plays in the progress of the project.
Elsewhere in his remarks, he stated that line one needs 2 BTSs (base transceiver station) which are being constructed by a European company.
He also stressed the Qom Urban Train Organization’s emphasis on the completion of the first phase of line one.
Moreover, the governor of Qom Bahram Sarmast also referred to Qom Metro project as one of the most important urban projects, calling for speeding up its implementation.
He had previously announced that the first phase of this project will be inaugurated in June 2021.