The deputy for Technical and Civil engineering of Qom Municipality stated that the project of the non-level Namaz intersection has more than 77% physical progress and it is expected that this project can be opened and made available to the citizens by the end of the year.
Abbas Halvaizadeh made the remarks referring to the latest status of the Namaz non-level intersection project.
The non-level and three-level intersection of the Namaz square on Jumori Boulevard with Ferdowsi Boulevard connects District 1 to District 4, he stated.
Noting that this project has more than 77% physical progress, he said that in the past few days, concrete pouring of the deck of this intersection has been completed and the digging operation of the square has started.
He pointed to the implementation problems of this project and added that one of the problems of this project was the relocation of the telecommunication basins, which the optical fiber of this area should be moved after the construction of level bridges.